S-34.1, r. 2 - Regulation respecting petroleum exploration, production and storage on land

Full text
245. A production licence holder must notify the Minister, at least 7 days before, of the date and time planned for the carrying out of the tests.
O.C. 1252-2018, s. 245.
In force: 2018-09-20
245. A production licence holder must notify the Minister, at least 7 days before, of the date and time planned for the carrying out of the tests.
O.C. 1252-2018, s. 245.